Our goal is to provide timely information to help you plan and manage your work during construction. These two-week projections outline construction activities, along with associated effects, including noise, dust, and vibration. Subscribe to receive an email when a new update is posted.

12/09 construction update

Since the last update in June the following work has been completed: 13,000 lineal feet of underground conduit were installed; 2,100 lineal feet of chilled water pipe were installed; 250 welds were x-rayed; 3,375 cubic yards of concrete for slurry wall were placed.

07/10 construction update

Beginning this week and through August 11 work is scheduled at the gas tanks between Buildings 24 and 38. While this work is underway the pathway at the underpass between Buildings 38 and 39 will be temporarily narrowed. On July 13 the walking path to the south and east of Building 31 is scheduled to close.

05/01 construction update

The Building 12 demolition work will be extended to Saturdays and additional 2nd shift. Saturday work will start on 3/28 and second shift work will start the week of 4/6. This extended schedule is expected to continue until the end of May
/ early July.

3/30 construction update

The Building 12 demolition work will be extended to Saturdays and additional 2nd shift. Saturday work will start on 3/28 and second shift work will start the week of 4/6. This extended schedule is expected to continue for the next 4 to 6 weeks.

2/13 construction update

Over the next two weeks, work is scheduled at the MIT.nano site to remove the bridge between Buildings 12 and 24. Some noise, dust, and vibration is expected. In the planning and execution of this work, crews are working to minimize these impacts.