10/3 construction forecast

schedule

Bldg. 13 Perimeter Site Fence

  • Viewing windows will be installed over the next 2 weeks.
  • Existing lighting along the north colonnade has been repaired.

Pedestrian Safety

  • Convex mirrors have been installed at blind corners of walkway and at Bldg. 9/13 crossing.
  • Installation of signage to discourage bike riding through perimeter walkways will be installed over the next 2 weeks.

Work zone map

General Information

Unforeseen condition – Existing Underground Utility Failure

  • Work continues repair the unexpected failure of an 8” water line.
  • See activity item 3 on the work zone map for reference.

Unforeseen condition – Bldg. 26 windows (west elevation)

  • Windows on the west elevation of 26 which were treated for acoustic mitigation have experienced and unexpected failure. We are working to resolve this and hope to re-open the pathway to Bldg. 24 in the coming weeks.

  • Updates will be communicated to the community as more detailed information becomes available.

Map of path closure