12/09 construction update

Two week look ahead

Site map

Recently complete enabling activities

Since the last update in June the following work has been completed:

  • 13,000 lineal feet of underground conduit were installed
  • 2,100 lineal feet of chilled water pipe were installed
  • 250 welds were x-rayed
  • 3,375 cubic yards of concrete for slurry wall were placed

Foundation diagram

Tower crane installation

Installation of the west tower crane will start on December 17, 2015 and continue through the weekend.

Tower crane installation

(left) West crane base prepped for installation; (right) Pre-planning layout schematic

Building 24 sidewalk closure

(12/7 - 1/4/16)

Work is underway to excavate part of the sidewalk on the north of Building 24 (facing Buildings 38-39). This section of sidewalk will be temporarily closed during this work, which is expected to conclude by January 4. Pedestrian traffic will be routed around the closure; the vehicular traffic lane and west side entrance will not be impacted.

Map showing sidewalk closure