12/24 construction forecast

 Two week look ahead

Site map

 

President’s Courtyard

Work will continue in the courtyard area for the next 2 weeks as the FP loop connection is finalized and existing sidewalk is repaired.

Main Lot Access

  • The utility work at the south end of Buildings 17 and 31 has restricted access from Vassar St.
  • Coordinated access for approved deliveries and handicap accessible parking in the Main Lot will be from Mass Ave. through Building 9.
  • This will be two-way traffic until further notice.

Main Lot access

Relocated Vehicle Access Gate

Please note that on Sunday, January 4, 2015 the parking gate at the driveway between Buildings 35 and 37 will be relocated to the driveway between Buildings 9 and 13. All remaining authorized Main Lot permit holders, maintenance and delivery vehicles should enter and exit the Main Lot via the Building 9 driveway on Mass Ave.