3/30 construction update

Schedule

Extended Work Hours

The Building 12 demolition work will be extended to Saturdays and additional 2nd shift. Saturday work will start on 3/28 and second shift work will start the week of 4/6. This extended schedule is expected to continue for the next 4 to 6 weeks.

Saturday 3/28/15

  • 6:00am to 6:00pm

Week of 3/30/15

  • 6:00am to 6:00pm

Saturday 4/4/15

  • 6:00am to 6:00pm

Week of 4/6/15

1st and 2nd shift work will start for the next 4 consecutive weeks

  • 1st shift 6:00am to 3:00pm
  • 2nd shift 3:00pm to 11:00pm

Building 12 Demolition

 demolition

Northwest corner of Building12

 demolition

Northwest corner of Building12

 Demolition

Installation of jet grout and secant piles