8/19 construction forecast

schedule

Interior work in Building 16

Item 1 in look ahead schedule. Installation of new 16″ chilled water lines on level 3 started on 8/18/14 and is scheduled to be complete in October. Working hours are 6:00am to 3:30pm. A temporary work barrier has been installed for safety.

 

map

The stairwell between Building 8 second floor and Building 16 third floor will be closed for the duration of this work. Signs in the area direct pedestrians to alternate stairwells and elevators nearby. The single elevator immediately next to the closed stairs will remain available for use by disabled individuals.