June 26, 2015
General Information
As you may have noticed from the outside looking in, the activity on the site has changed focus over the last few weeks. We are in the final stage of the utility enabling phase at the same time we are ramping up for the building phase.
- Some interesting facts related to the Enabling phase:
- Over 20,000 lf of rigid conduit installed
- 2,100 lf of welded Chilled Water Pipe installed
- 250 X-rayed welds completed and tested
- Over 2,500 lf of Civil Piping installed (water, drain, sewer)
- Over 5,000 tons of construction waste and Building 12 debris hauled away (99% recycling rate)
- Over 2,000 lf of concrete encased piping removed from under Building 12 slab
- Over 1,000 lf of Ductbank removed