Bldg. 13 Perimeter Site Fence
Additional viewing windows will be installed at a lower elevation based on feedback from MIT community.
Pedestrian Safety
Installation of signage to discourage bike riding through perimeter walkways will be installed over the next 2 weeks.
General Information
Unforeseen condition – Existing Underground Utility Failure:
- Work continues repair the unexpected failure of an 8” water line.
- See activity item 5 on the work zone map for reference.
- Expected completion date for this scope is 10/27/14.
Unforeseen condition – Bldg. 26 windows (west elevation): Windows on the west elevation of 26 which were treated for acoustic mitigation have experienced and unexpected failure. We are working to resolve this and hope to re-open the pathway to Bldg. 24 in the coming weeks.
Update: Repair work continues and a plan is in place to replace failed single pane glazing with new insulated units.
Main Lot – Installation of utility infrastructure for Construction Trailers:
- Utility work will continue over the next 2 weeks to prepare Main Lot for the installation of construction field offices.
- Work associated with this activity will be noisy at times due to vehicle back-up alarms saw cutting for formwork and general carpentry items.
Presidents Courtyard – Work Zone H:
- Installation of new fire protection line in work zone H is projected to start the week of 11/10/14.
- A detailed schedule of the work scope and community impact will be sent out as a campus wide notification in the next 2 weeks.