11/3 construction forecast

2 week look ahead

 

work zones

Pedestrian Safety

Signage to discourage bike riding through perimeter walkways will be installed the week of 11/3/14.

General Information

Unforeseen condition: Existing Underground Utility Failure (activity item 5). Pathway at Bldg. 26 breezeway will re-open the week of 11/3/14. Thank you for your patience!

Path closure

Main Lot – Installation of Construction Trailers:

  • Utility work to enable the site for the trailer installation will continue over the next 2 to 3 weeks.
  • Following the completion of the utility installation, the trailers will be mobilized and installation of phase 1 will begin. This activity will have duration of 3 to 4 weeks.
  • Work associated with these activities will be noisy at times due to vehicle back-up alarms saw cutting for form work and general carpentry items.

Presidents Courtyard – Work Zone H:

  • Installation of new fire protection line in work zone H is projected to start the week of 11/10/14.

Progress photos

Utility work at Building 5 and 7

Underground temporary utilities at the corner of Buildings 5 and 7

New ductbank

 

 

New 8-way electrical ductbank at the north side of Building 12 (Activity items 11 and 12)