Main Lot Access
- The utility work at the south end of Buildings 17 and 31 has restricted access from Vassar Street.
- Coordinated access for approved deliveries and handicap accessible parking in the Main Lot will be from Mass Ave through Building 9.
- This will be two-way traffic until further notice.
Pedestrian Access – South side of Building 31
Starting Monday, January 19 through Wednesday, February 4, access will be restricted due to installation of site utilities.