1/16 construction update

Two week look ahead

Zone map

Main Lot Access

  • The utility work at the south end of Buildings 17 and 31 has restricted access from Vassar Street.
  • Coordinated access for approved deliveries and handicap accessible parking in the Main Lot will be from Mass Ave through Building 9.
  • This will be two-way traffic until further notice.

Main Lot map

Pedestrian Access – South side of Building 31

Starting Monday, January 19 through Wednesday, February 4, access will be restricted due to installation of site utilities.

Building 31 access