January 30, 2015
Main Lot Access
- The utility work at the south end of Buildings 17 and 31 has restricted access from Vassar St.
- Coordinated access for approved deliveries and handicap accessible parking in the Main Lot will be from Mass Ave through Building 9.
- This will be two-way traffic until further notice.
Pedestrian Access – South Side if Building 31
Starting on 1/19/15 through 2/4/15 access will be restricted due to installation of site utilities.
(left) Gate 3 and (right) Gate 1
Building 16 – Eastman Court Entrance
- Entrance will be closed due to installation of temporary 15KV power cables from MH29 to MH36.
- Work is scheduled to start the week of 1/19/15 and continue through the week of 2/1/15.
- Pedestrian traffic will experience minor re-routing restrictions during cable pull operation.