1/30 construction update

Two week look ahead

 

zone map

 

Main Lot Access

  • The utility work at the south end of Buildings 17 and 31 has restricted access from Vassar St.
  • Coordinated access for approved deliveries and handicap accessible parking in the Main Lot will be from Mass Ave through Building 9.
  • This will be two-way traffic until further notice.

Mail Lot access

Pedestrian Access – South Side if Building 31

Starting on 1/19/15 through 2/4/15 access will be restricted due to installation of site utilities.

Pedestrian access

Construction photos

(left) Gate 3 and (right) Gate 1

Building 16 – Eastman Court Entrance

  • Entrance will be closed due to installation of temporary 15KV power cables from MH29 to MH36.
  • Work is scheduled to start the week of 1/19/15 and continue through the week of 2/1/15.
  • Pedestrian traffic will experience minor re-routing restrictions during cable pull operation.

Eastman Court