January 9, 2015
Main Lot Access
- Due to utility work at the south end of Buildings 17 and 31 vehicular access from Vassar St has been restricted.
- Coordinated access for approved deliveries and handicap accessible parking in the Main Lot will be from Mass Ave through Building 9.
- This will be two-way traffic until further notice.
Pedestrian access to South side of Building 31
Starting on 1/19/15 through 2/4/15 access will be restricted due to installation of site utilities.
Activity Item 1 – Building 4 Cut and Cap Utilities for Bridge Removal
- A temporary partition will be installed on Saturday 1/10/15 to enable work scope.
- Café 4 will remain open through work scope execution.