1/9 construction forecast

schedule

Zone map

Main Lot Access

  • Due to utility work at the south end of Buildings 17 and 31 vehicular access from Vassar St has been restricted.
  • Coordinated access for approved deliveries and handicap accessible parking in the Main Lot will be from Mass Ave through Building 9.
  • This will be two-way traffic until further notice.

Main Lot Access

Pedestrian access to South side of Building 31

Starting on 1/19/15 through 2/4/15 access will be restricted due to installation of site utilities.

Access to Building 31

 Activity Item 1 – Building 4 Cut and Cap Utilities for Bridge Removal

  • A temporary partition will be installed on Saturday 1/10/15 to enable work scope.
  • Café 4 will remain open through work scope execution.