August 1, 2014
Interior work in Building 16
Item 1 in look ahead schedule. Installation of new 16” chilled water lines on level 3 will start on 8/18/14 and is scheduled to be complete in early October. Working hours are 6:00am to 3:30pm. A temporary work barrier will be installed for safety.