8/29 construction forecast

Interior work in building 16

Item 1 in look ahead schedule.

Installation of new 16” chilled water lines on level 3 started on 8/18/14 and is scheduled to be complete in early October. Working hours are 6:00am to 3:30pm.

A temporary work barrier has been installed for safety.

Passage between buildings 16 and 8 will be altered at level 3 and level 2 for the duration of this work scope. A detailed plan of the altered route was sent out to the MIT community last week.

 

sample schedule

sample map