9/22 construction forecast

Vassar Street road work

In the next 2 to 3 weeks, Vassar Street construction will resume along with a detour for vehicle traffic.

Schedule

MIT.nano work zones

mapVassar Street road work. In the next 2 to 3 weeks, Vassar Street construction will resume along with a detour for vehicle traffic. This work is required to install the new 30” chilled water lines (supply and return) and new 10” fire protection main.
mapBased on the current schedule the Vassar street scope of work will be complete by mid to late December of this year. The detour will be configured in the same format as the first phase.
mapPlease note that two-way local traffic is open from Main Street for access to the Stata parking garage.