The Process Cooling Water (PCW) replacement project schedule has been finalized. This allows us to optimize the remaining Phase II tool move dates throughout the summer.
As a reminder, the current up-to-date tool move schedule can be found at web.mit.edu/scholvin/www/nanomove/
MIT.nano will procure a temporary chiller that enables us to move the AJA-TRL and EBeamFP in early June (to get them moved before humidity in the summer may have an impact on them). Other less humidity-critical Phase II tool moves are scheduled to coincide with the PCW completion and turnover (to minimize tool downtime).
The low zone (Level 1 cleanroom/basement) is scheduled for early July, with the high zone (Level 3 and Level 5) following in early August.
As always, please contact us at mitnano-feedback@mit.edu with any questions, comments or concerns.