July 18, 2014
Door closures and pathways
Blue dots indicate doors which have closed and dashed blue lines indicate available pedestrian pathways.
Building 13 west entry
A temporary asphalt ramp was installed at the west entry of building 13, thank you for your patience!
Bike parking relocation
In the next 1 to 2 weeks some of the existing bicycle racks at the building 26 underpass will be relocated to enable the removal of the existing concrete slab to accommodate a new utility areaway. The project team will work with the Parking & Transportation Office to notify the community and allow for the removal of any bicycles that may be attached to the affected racks.