Facility Updates

8/19 construction forecast

Interior work in Building 16: Installation of new 16″ chilled water lines on level 3 started on 8/18/14 and is scheduled to be complete in October. Working hours are 6:00am to 3:30pm. A temporary work barrier has been installed for safety.

8/1 construction forecast

Passage between buildings 16 and 8 will be altered at level 3 and level 2 for the duration of this work scope. A detailed plan of the altered route will be sent out to the MIT community next week.

7/25 construction forecast

MIT.nano project updates will be issued on a weekly basis throughout the duration of the project and will provide a two-week look ahead outlining projected activities.