Facility Updates

05/01 construction update

The Building 12 demolition work will be extended to Saturdays and additional 2nd shift. Saturday work will start on 3/28 and second shift work will start the week of 4/6. This extended schedule is expected to continue until the end of May / early July.

3/30 construction update

The Building 12 demolition work will be extended to Saturdays and additional 2nd shift. Saturday work will start on 3/28 and second shift work will start the week of 4/6. This extended schedule is expected to continue for the next 4 to 6 weeks.

3/6 construction update

Building 12A demolition (end February) - Complete Building 24 bridge demolition (early March) - Complete Building 4 bridge demolition (early March) - Complete

2/23 construction update

The demolition of the bridge between Buildings 12 and 24 has been rescheduled and is now anticipated to begin approximately February 28. Duration of work is approximately two weeks.

2/13 construction update

Over the next two weeks, work is scheduled at the MIT.nano site to remove the bridge between Buildings 12 and 24. Some noise, dust, and vibration is expected. In the planning and execution of this work, crews are working to minimize these impacts.

1/30 construction update

Starting on January 19 through February 4 access to the south side of Building 31 will be restricted due to installation of site utilities. The entrance to Building 16 at Eastman Court will be closed until February 1 due to installation of power cables.

1/16 construction update

Starting Monday, January 19 through Wednesday, February 4, access around the south side of Building 31 will be restricted due to installation of site utilities.

1/9 construction forecast

Due to the utility work at the south end of Buildings 17 and 31 vehicular access from Vassar Street has been restricted. Starting on January 19 through February 4 pedestrian access will be restricted around the south side of Building 31.